Georgia Power recently said because of vibrations in the reactor’s cooling system, Unit 4 would not start commercial operation until sometime in the second quarter of 2024.
The utility said its current load growth projections through 2030-2031 are 17 times higher than what it forecasted in its 2022 Integrated Resource Plan.
The in-service date for Plant Vogtle Unit 4 is being pushed back to the first quarter of 2024 due to a motor fault in one of four reactor coolant pumps, Georgia Power said in a filing to the SEC.
The projected schedule for Unit 3 primarily depends on pre-operational testing and start-up, which may be impacted by further equipment or other operational cha…
Georgia Power announced that hot functional testing began at Vogtle Unit 4, marking one of the final steps for the new nuclear unit ahead of fuel loading. Hot f…